1.
Before
2.
Ground braking June 18
3.
June 20
4.
Excavation June 21
5.
Footing June 23
6.
More footing June 25 & 30
7.
Footing for storage
room July 2
8. Air
conditioner moved and new storage room wall set July 18
9. Sub floor July 19
& 20
10. Sub
floor completed July 24
11. Preparing existing wall for adding new room,
July 25
12. Walls and sewer,
July 26
13. More wall stuff and sewer done,
July 27
14.
All walls up, rafters up, rest room, July 31
15.
Roof, August 1
16.
Tar paper, outside covering, concrete forms, August 2
17. Concrete, doors and windows, August 4,
through August 8
18.
Storage room progress, August 9 & 10
19.
Roofing and second porch, August 14 & 16
20. Drainage channel,
electrical & siding. Aug. 20 thru Sept. 4
21.
Insulation, electrical, siding and plumbing for both rooms, Sept. 8
22.
Final siding installation, prep for wallboard inside. Sept. 10 & 11
23. Check-in window moved. Sept. 13
& 14
24.
Walls painted, flooring in and light fixtures installed Sept. 24, 25, 28 &
28
25.
Final paint and trim. October 05 plus New Sign 13/01/07 last 4
pictures.